Monday, July 5, 2010

Heat, Stairs & Tile

The heat has been totally crazy here - in the 90's and just horrible to work in.

Rob has finished painting the master bed & bath, the office & upstairs hallway.

We have real stairs! The railing spindles still need to go in, then some trim will need to be painted & the treads & railing need to be polyurethaned.

Mudroom is painted & tile should be finished today, then grout has to go down & be sealed, and baseboard trim needs to go up & be painted.

Hopefully the temps will cool down, and hardwood floors & master bath tile can get done soon. We're almost there!

4 weeks until the baby is due . . .